Markdown

---
gsd_state_version: 1.0
milestone: v1.0
milestone_name: Analytics & Monitoring
status: shipped
last_updated: "2026-02-25"
progress:
total_phases: 5
completed_phases: 5
total_plans: 10
completed_plans: 10
---
# Project State
## Project Reference
See: .planning/PROJECT.md (updated 2026-02-25)
**Core value:** When something breaks — an API key expires, a service goes down, a credential needs reauthorization — the admin knows immediately and knows exactly what to fix.
**Current focus:** v1.0 shipped — next milestone not yet defined
## Current Position
Phase: 5 of 5 (all complete)
Plan: All plans complete
Status: v1.0 milestone shipped
Last activity: 2026-02-25 — v1.0 milestone archived
Progress: [██████████] 100%
## Performance Metrics
**Velocity:**
- Total plans completed: 10
- Timeline: 2 days (2026-02-24 → 2026-02-25)
**By Phase:**
| Phase | Plans | Total | Avg/Plan |
|-------|-------|-------|----------|
| 01-data-foundation | 2 | ~34 min | ~17 min |
| 02-backend-services | 4 | ~51 min | ~13 min |
| 03-api-layer | 2 | ~16 min | ~8 min |
| 04-frontend | 2 | ~4 min | ~2 min |
| 05-tech-debt-cleanup | — | direct commit | — |
## Accumulated Context
### Decisions
All v1.0 decisions validated — see PROJECT.md Key Decisions table for outcomes.
### Pending Todos
None.
### Blockers/Concerns
None — v1.0 shipped.
## Session Continuity
Last session: 2026-02-25
Stopped at: v1.0 milestone archived and tagged
Resume file: None